D.20.31 - Sanitary WasteΒΆ

The following models are available:

D.20.31.011b | Sanitary Waste Piping - Cast Iron w/flexible couplings, SDC A,B, BRACING FRAGILITY

Costing based upon 1000 ft segments of pipe
Construction Quality: Normal
Seismic Installation Conditions: SDC A or B
Notes: Consequence is for piping only. Enter floor wetting consequence seperately. Cost includes allowance for MEP relocation to perform work.

Suggested Block Size: 1000 LF

The following repair consequences are available for this model:

Carbon

Cost

Energy

Time


D.20.31.012b | Sanitary Waste Piping - Cast Iron w/flexible couplings, SDC C, BRACING FRAGILITY

Costing based upon 1000 ft segments of pipe
Construction Quality: Normal
Seismic Installation Conditions: SDC C
Notes: Consequence is for piping only. Enter floor wetting consequence seperately. Cost includes allowance for MEP relocation to perform work.

Suggested Block Size: 1000 LF

The following repair consequences are available for this model:

Carbon

Cost

Energy

Time


D.20.31.013b | Sanitary Waste Piping - Cast Iron w/flexible couplings, SDC D,E,F, BRACING FRAGILITY

Costing based upon 1000 ft segments of pipe
Construction Quality: Normal
Seismic Installation Conditions: SDC D, E or F (high seismic design)
Notes: Consequence is for piping only. Enter floor wetting consequence seperately. Cost includes allowance for MEP relocation to perform work.

Suggested Block Size: 1000 LF

The following repair consequences are available for this model:

Carbon

Cost

Energy

Time


D.20.31.014b | Sanitary Waste Piping - Cast Iron w/flexible couplings, SDC D,E,F (OSHPD or sim), BRACING FRAGILITY

Costing based upon 1000 ft segments of pipe
Construction Quality: Special Regulation (e.g. OSHPD) for piping installations
Seismic Installation Conditions: SDC D, E or F (high seismic design)
Notes: Consequence is for piping only. Enter floor wetting consequence seperately. Cost includes allowance for MEP relocation to perform work.

Suggested Block Size: 1000 LF

The following repair consequences are available for this model:

Carbon

Cost

Energy

Time


D.20.31.021a | Sanitary Waste Piping - Cast Iron w/bell and spigot couplings, SDC A,B, PIPING FRAGILITY

Costing based upon 1000 ft segments of pipe
Construction Quality: Normal
Seismic Installation Conditions: SDC A or B
Notes: Consequence is for piping only. Enter floor wetting consequence seperately. Cost includes allowance for MEP relocation to perform work.

Suggested Block Size: 1000 LF

The following repair consequences are available for this model:

Carbon

Cost

Energy

Time


D.20.31.021b | Sanitary Waste Piping - Cast Iron w/bell and spigot couplings, SDC A,B, BRACING FRAGILITY

Costing based upon 1000 ft segments of pipe
Construction Quality: Normal
Seismic Installation Conditions: SDC A or B
Notes: Consequence is for piping only. Enter floor wetting consequence seperately. Cost includes allowance for MEP relocation to perform work.

Suggested Block Size: 1000 LF

The following repair consequences are available for this model:

Carbon

Cost

Energy

Time


D.20.31.022a | Sanitary Waste Piping - Cast Iron w/bell and spigot couplings, SDC C, PIPING FRAGILITY

Costing based upon 1000 ft segments of pipe
Construction Quality: Normal
Seismic Installation Conditions: SDC C
Notes: Consequence is for piping only. Enter floor wetting consequence seperately. Cost includes allowance for MEP relocation to perform work.

Suggested Block Size: 1000 LF

The following repair consequences are available for this model:

Carbon

Cost

Energy

Time


D.20.31.022b | Sanitary Waste Piping - Cast Iron w/bell and spigot couplings, SDC C, BRACING FRAGILITY

Costing based upon 1000 ft segments of pipe
Construction Quality: Normal
Seismic Installation Conditions: SDC C
Notes: Consequence is for piping only. Enter floor wetting consequence seperately. Cost includes allowance for MEP relocation to perform work.

Suggested Block Size: 1000 LF

The following repair consequences are available for this model:

Carbon

Cost

Energy

Time


D.20.31.023a | Sanitary Waste Piping - Cast Iron w/bell and spigot couplings, SDC D,E,F, PIPING FRAGILITY

Costing based upon 1000 ft segments of pipe
Construction Quality: Normal
Seismic Installation Conditions: SDC D, E or F (high seismic design)
Notes: Consequence is for piping only. Enter floor wetting consequence seperately. Cost includes allowance for MEP relocation to perform work.

Suggested Block Size: 1000 LF

The following repair consequences are available for this model:

Carbon

Cost

Energy

Time


D.20.31.023b | Sanitary Waste Piping - Cast Iron w/bell and spigot couplings, SDC D,E,F, BRACING FRAGILITY

Costing based upon 1000 ft segments of pipe
Construction Quality: Normal
Seismic Installation Conditions: SDC D, E or F (high seismic design)
Notes: Consequence is for piping only. Enter floor wetting consequence seperately. Cost includes allowance for MEP relocation to perform work.

Suggested Block Size: 1000 LF

The following repair consequences are available for this model:

Carbon

Cost

Energy

Time


D.20.31.024a | Sanitary Waste Piping - Cast Iron w/bell and spigot couplings, SDC D,E,F (OSHPD or sim), PIPING FRAGILITY

Costing based upon 1000 ft segments of pipe
Construction Quality: Special Regulation (e.g. OSHPD) for piping installations
Seismic Installation Conditions: SDC D, E or F (high seismic design)
Notes: Consequence is for piping only. Enter floor wetting consequence seperately. Cost includes allowance for MEP relocation to perform work.

Suggested Block Size: 1000 LF

The following repair consequences are available for this model:

Carbon

Cost

Energy

Time


D.20.31.024b | Sanitary Waste Piping - Cast Iron w/bell and spigot couplings, SDC D,E,F (OSHPD or sim), BRACING FRAGILITY

Costing based upon 1000 ft segments of pipe
Construction Quality: Special Regulation (e.g. OSHPD) for piping installations
Seismic Installation Conditions: SDC D, E or F (high seismic design)
Notes: Consequence is for piping only. Enter floor wetting consequence seperately. Cost includes allowance for MEP relocation to perform work.

Suggested Block Size: 1000 LF

The following repair consequences are available for this model:

Carbon

Cost

Energy

Time